Broad Street Bridge preventive maintenance project to cause closures

Local News
BROAD.STREET.BRIDGE_1507323701054.jpg

The Broad Street bridge will be closed to traffic from 7 a.m. until 6 p.m. Wednesday, October 11 as the Broad Street Bridge Preventive Maintenance Project continues.

During the evening, after 6 p.m., one lane in each direction will be open. Temporary and partial traffic lane and sidewalk closures are expected to occur until the end of November. 

According to the City of Rochester, weather or other delays may cause the bridge to be closed during the same hours on Thursday and Friday. 

The City says that drivers and pedestrians should expect traffic delays at either side of the bridge at South Avenue and Exchange Street during this time. The Court Street and Main Street bridges may be used as detours. 

The Broad Street Bridge Preventive Maintenance Project involves:

  • concrete repairs at bridge substructures;
  • drainage repairs;
  • new bridge railing;
  • replacement of sidewalks;
  • bridge deck rehabilitation;
  • and approach street milling and paving with new sidewalks, curbing and street lighting. 
     